Judgment of the General Court (Seventh Chamber) of 7 July 2010. # European Commission v Antiche Terre Soc. coop. rl Società Agricola Cooperativa. # Arbitration clause - Programme concerning the promotion of energy technologies for Europe (Thermie) - Contract concerning the project for the building in Umbertide (Italy) of an electricity generating plant using an innovative agro-forestry biomass combustion technology - Substantial amendment to the conditions for performance of the contract - Termination - Reimbursement of sums paid - Interest. # Case T-51/09.

ECLI:EU:T:2010:288

62009TJ0051

July 7, 2010
With Google you find a lot.
With us you find everything. Try it now!

I imagine what I want to write in my case, I write it in the search engine and I get exactly what I wanted. Thank you!

Valentina R., lawyer

(Case T-51/09)

Arbitration clause – Programme concerning the promotion of energy technologies for Europe (Thermie) – Contract concerning the project for the building in Umbertide (Italy) of an electricity generating plant using an innovative agro-forestry biomass combustion technology – Substantial amendment to the conditions for performance of the contract – Termination – Reimbursement of sums paid – Interest

Procedure – Referral to the General Court under an arbitration clause (Art. 238 EC) (see paras 46, 50-60, 79-82, 85)

Re:

ACTION brought by the Commission under Article 238 EC seeking an order that Antiche Terre reimburse the sums paid by the Community in performance of contract no BM/188/96 of 23 December 1996, concluded with three companies, including Antiche Terre, under the Thermie programme.

Operative part

The Court:

1.Orders Antiche Terre Soc. Coop. rl Società Agricola to pay the European Commission the sum of EUR 479 332.40, together with late-payment interest at the Italian statutory rate, calculated in accordance with the rates applicable from 4 January 2004 until payment in full of the debt, after deduction of the sum of EUR 461 979 recovered by the Commission following the implementation on 25 January 2005 of the bank guarantee of which it was beneficiary;

2.Dismisses the remainder of the action;

3.Orders Antiche Terre to pay the costs.

EurLex Case Law

AI-Powered Case Law Search

Query in any language with multilingual search
Access EUR-Lex and EU Commission case law
See relevant paragraphs highlighted instantly

Get Instant Answers to Your Legal Questions

Cancel your subscription anytime, no questions asked.Start 14-Day Free Trial

At Modern Legal, we’re building the world’s best search engine for legal professionals. Access EU and global case law with AI-powered precision, saving you time and delivering relevant insights instantly.

Contact Us

Tivolska cesta 48, 1000 Ljubljana, Slovenia