Application for interim measures – Control of concentrations between undertakings – Urgency
3. Applications for interim measures – Interim relief – Conditions for granting – Urgency – Serious and irreparable damage (Art. 243 EC) (see paras 37-40)
Re:
APPLICATION for an order, first, for suspension of the operation of the Commission’s letter of 15 November 2005 declaring that a concentration between Gas Natural SDG, SA, and Endesa, SA, does not have a Community dimension within the meaning of Council Regulation (EC) No 139/2004 of 20 January 2004 on the control of concentrations between undertakings (OJ 2004 L 24, p. 1), and, secondly, for the adoption of other interim measures
The Court:
1.Dismisses the application for interim measures;
2.Reserves the costs.