Judgment of the Court of 24 May 1988. # Commission of the European Communities v Kingdom of Belgium. # Technical requirements for inland waterway vessels. # Case 307/86.

ECLI:EU:C:1988:253

61986CJ0307

May 24, 1988
With Google you find a lot.
With us you find everything. Try it now!

I imagine what I want to write in my case, I write it in the search engine and I get exactly what I wanted. Thank you!

Valentina R., lawyer

Avis juridique important

61986J0307

European Court reports 1988 Page 02677

Summary

A Member State may not plead provisions, practices or circumstances existing in its internal legal system to justify a failure to comply with obligations and time-limits laid down in directives.

Parties

In Case 307/86

Commission of the European Communities, represented by Jean Amphoux, Legal Adviser, acting as Agent, with an address for service in Luxembourg at the office of G . Kremlis, a member of the Commission' s Legal Department, Jean Monnet Building, Kirchberg

applicant,

Kingdom of Belgium, represented by the Minister for External Relations, and Jan Devadder, Assistant Counsellor at the Ministry of Foreign Affairs, Foreign Trade and Cooperation with Developing Countries, acting as its Agent, with an address for service in Luxembourg at its Embassy, Résidence Champagne, 4 rue de Girondins,

defendant,

APPLICATION for a declaration that, by failing to adopt within the prescribed period the laws, regulations or administrative provisions necessary to comply with Council Directive 82/714/EEC of 4 October 1982 laying down technical requirements for inland waterway vessels, the Kingdom of Belgium has failed to fulfil its obligations under the Treaty,

composed of : Lord Mackenzie Stuart, President, G . Bosco and G . C . Rodríguez Iglesias ( Presidents of Chambers ), T . Koopmans, U . Everling, Y . Galmot, C . Kakouris, R . Joliet and F . Schockweiler, Judges,

Advocate General : J . Mischo

Registrar : B . Pastor, Administrator

having regard to the Report for the Hearing and further to the hearing on

17 March 1988,

after hearing the Opinion of the Advocate General delivered at the sitting on 17 March 1988,

gives the following

By an application lodged at the Court Registry on 5 December 1986, the Commission of the European Communities brought an action under Article 169 of the EEC Treaty for a declaration that, by failing to adopt within the prescribed period the laws, regulations or administrative provisions necessary to comply with Council Directive 82/714/EEC of 4 October 1982 ( Official Journal 1982, L 301, p . 1 ) laying down technical requirements for inland waterway vessels, the Kingdom of Belgium has failed to fulfil its obligations under the EEC Treaty.

The aim of Directive 82/714/EEC is to establish common rules regarding the technical requirements with which inland waterway vessels must comply. The adoption of these common rules had already been provided for in Council Directive 76/13/EEC of 20 January 1976 on reciprocal recognition of navigability licences for inland waterway vessels ( Official Journal 1976, L 21, p . 10 ). According to Article 22 of Directive 82/714/EEC, Member States were to adopt, after consulting the Commission, the provisions necessary to comply with the directive not later than 1 January 1985.

Since the Commission had not received any communication from the Belgian Government within the prescribed period, concerning the measures for implementing the directive in question, it addressed to that Government, on 3 June 1985, a formal notice requesting it to submit, within two months, its observations on the matter. The Belgian Government' s observations, which were communicated by letter of 3 September 1985, were not regarded as satisfactory by the Commission, which, accordingly, on 3 June 1986, delivered a reasoned opinion pursuant to the first paragraph of Article 169 of the EEC Treaty. As that opinion met with no reply, the Commission brought the present action for a declaration that Belgium had failed to fulfil its obligations under the Treaty.

Reference is made to the Report for the Hearing for a fuller account of the facts of the case, the course of the proceedings and the submissions and arguments of the parties, which are mentioned or discussed hereinafter only in so far as is necessary for the reasoning of the Court.

The Belgian Government acknowledges that it has not yet adopted the domestic measures necessary to implement the directive. It states that the problem of determining which authorities are to be responsible for issuing the Community certificates attesting conformity, introduced by the directive, and the necessity of coordinating different domestic regulations delayed the preparation of a draft royal decree to transpose the directive into Belgian law. At the hearing it indicated that this draft had been prepared, but that difficulties which had arisen in the mean time had delayed its adoption.

In that respect, it should be pointed out that, as the Court has consistently held, a Member State cannot plead provisions, practices or circumstances existing in its national legal system to justify the failure to comply with obligations and time-limits laid down in directives.

It must therefore be declared that, by failing to adopt within the prescribed period the provisions necessary to comply with Council Directive 82/714/EEC of 4 October 1982 laying down technical requirements for inland waterway vessels, the Kingdom of Belgium has failed to fulfil its obligations under the Treaty.

Decision on costs

Costs

Under Article 69 ( 2 ) of the Rules of Procedure, the unsuccessful party is to be ordered to pay the costs. Since the defendant has failed in its submissions, it must be ordered to pay the costs.

Operative part

On those grounds,

hereby :

( 1 ) Declares that, by failing to adopt within the prescribed period the provisions necessary to comply with Council Directive 82/714/EEC of 4 October 1982 laying down technical requirements for inland waterway vessels, the Kingdom of Belgium has failed to fulfil its obligations under the EEC Treaty;

( 2 ) Orders the Kingdom of Belgium to pay the costs.

EurLex Case Law

AI-Powered Case Law Search

Query in any language with multilingual search
Access EUR-Lex and EU Commission case law
See relevant paragraphs highlighted instantly

Get Instant Answers to Your Legal Questions

Cancel your subscription anytime, no questions asked.Start 14-Day Free Trial

At Modern Legal, we’re building the world’s best search engine for legal professionals. Access EU and global case law with AI-powered precision, saving you time and delivering relevant insights instantly.

Contact Us

Tivolska cesta 48, 1000 Ljubljana, Slovenia