(Case T-298/16) (*)
((Non-contractual liability - Instrument for Pre-Accession Assistance - Third country - National public procurement - Devolved management - Decision 2008/969/EC, Euratom - Early Warning System (EWS) - Activation of a warning in the EWS - Protection of the financial interests of the European Union - Commission’s refusal to give ex ante approval - Contract not awarded - Jurisdiction of the General Court - Admissibility of evidence - No legal basis for the warning - Rights of defence - Presumption of innocence - Sufficiently serious breach of a rule of law conferring rights on individuals - Causal link - Material and non-material damage - Loss of the contract - Loss of the opportunity to be awarded other contracts))
(2019/C 93/49)
Language of the case: French
Applicant: East West Consulting SPRL (Nandrin, Belgium) (represented by: initially L. Levi and A. Tymen, and subsequently L. Levi, lawyers)
Defendant: European Commission (represented by: F. Dintilhac and J. Estrada de Solà, acting as Agents)
Application under Article 268 TFEU seeking compensation for the material and non-material harm allegedly suffered by the applicant as a result of a warning being activated against it in the Early Warning System (EWS) and the subsequent refusal, on the basis of that warning, to endorse the contract awarded, following a public procurement procedure, to the consortium which it led and which was to be financed by the European Union in the context of the Instrument for Pre-Accession Assistance (IPA).
The Court:
1.Orders the European Commission to pay to East West Consulting SPRL the sum of EUR 20 000;
2.Dismisses the action as to the remainder;
3.Orders each party to bear its own costs.
(*)
Language of the case: French.
ECLI:EU:C:2019:140