I imagine what I want to write in my case, I write it in the search engine and I get exactly what I wanted. Thank you!
Valentina R., lawyer
(Arbitration clause - Contract for financial assistance concluded under a specific programme in the field of telematic applications of common interest - Encata Project - Reimbursement of sums advanced - Late-payment interest - Default procedure)
(2009/C 32/63)
Language of the case: Portuguese
Applicant: Commission of the European Communities (represented by: M. Afonso, acting as Agent)
Defendant: Cooperação e Desenvolvimento Regional, SA (Setúbal, Portugal)
Action under Article 238 EC seeking an order that the defendant reimburse part of the amount advanced by the European Community, together with late-payment interest, under contract SU 1001 (SU) Encata.
The Court:
1.Orders Cooperação e Desenvolvimento Regional, SA to reimburse to the Commission of the European Communities the sum of EUR 63 349,27, together with late-payment interest:
—at the rate of 6.29 % per annum from 31 January 2001 to the date of the present judgment;
—at the annual rate applied under Irish law, that is to say, currently Article 26 of the Debtors (Ireland) Act 1840, as amended, up to the rate of 6.29 % per annum from the date of the present judgment to full clearance of the debt;
2.Orders Cooperação e Desenvolvimento Regional to pay the costs.
* * *
(1) OJ C 183, 19.7.2008.