EUR-Lex & EU Commission AI-Powered Semantic Search Engine
Modern Legal
  • Query in any language with multilingual search
  • Access EUR-Lex and EU Commission case law
  • See relevant paragraphs highlighted instantly
Start free trial

Similar Documents

Explore similar documents to your case.

We Found Similar Cases for You

Sign up for free to view them and see the most relevant paragraphs highlighted.

Case T-174/08: Judgment of the Court of First Instance of 17 December 2008 — Commission v Cooperação e Desenvolvimento Regional (Arbitration clause — Contract for financial assistance concluded under a specific programme in the field of telematic applications of common interest — Encata Project — Reimbursement of sums advanced — Late-payment interest — Default procedure)

ECLI:EU:UNKNOWN:62008TA0174

62008TA0174

January 1, 2008
With Google you find a lot.
With us you find everything. Try it now!

I imagine what I want to write in my case, I write it in the search engine and I get exactly what I wanted. Thank you!

Valentina R., lawyer

Official Journal of the European Union

C 32/33

(Case T-174/08)

(Arbitration clause - Contract for financial assistance concluded under a specific programme in the field of telematic applications of common interest - Encata Project - Reimbursement of sums advanced - Late-payment interest - Default procedure)

(2009/C 32/63)

Language of the case: Portuguese

Parties

Applicant: Commission of the European Communities (represented by: M. Afonso, acting as Agent)

Defendant: Cooperação e Desenvolvimento Regional, SA (Setúbal, Portugal)

Re:

Action under Article 238 EC seeking an order that the defendant reimburse part of the amount advanced by the European Community, together with late-payment interest, under contract SU 1001 (SU) Encata.

Operative part of the judgment

The Court:

1.Orders Cooperação e Desenvolvimento Regional, SA to reimburse to the Commission of the European Communities the sum of EUR 63 349,27, together with late-payment interest:

at the rate of 6.29 % per annum from 31 January 2001 to the date of the present judgment;

at the annual rate applied under Irish law, that is to say, currently Article 26 of the Debtors (Ireland) Act 1840, as amended, up to the rate of 6.29 % per annum from the date of the present judgment to full clearance of the debt;

2.Orders Cooperação e Desenvolvimento Regional to pay the costs.

* * *

(1) OJ C 183, 19.7.2008.

EurLex Case Law

AI-Powered Case Law Search

Query in any language with multilingual search
Access EUR-Lex and EU Commission case law
See relevant paragraphs highlighted instantly

Get Instant Answers to Your Legal Questions

Cancel your subscription anytime, no questions asked.Start 14-Day Free Trial

At Modern Legal, we’re building the world’s best search engine for legal professionals. Access EU and global case law with AI-powered precision, saving you time and delivering relevant insights instantly.

Contact Us

Tivolska cesta 48, 1000 Ljubljana, Slovenia