((Interim measures - Public works contracts - Tendering procedure - Construction and maintenance of a tri-generation plant - Rejection of tender submitted by a tenderer and award of the contract to another tenderer - Application for suspension of operation of a measure - Prima facie case - Lack of urgency))
(2015/C 155/33)
Language of the case: Italian
Applicant: Europower SpA (Milan, Italy) (represented by: G. Cocco and L. Salomoni, lawyers)
Defendant: European Commission (represented by: L. Cappelletti, L. Di Paolo and F. Moro, acting as Agents)
Application, in essence, for suspension of operation of the decision of 3 April 2014 in which the Commission rejected the tender submitted by Europower in tendering procedure JRC IPR 2013 C04 0031 OC for the construction and maintenance of a tri-generation plant with a gas turbine on the Ispra (Italy) site of its Joint Research Centre (JRC) (OJ 2013/S 137-237146) and awarded the contract to CPL Concordia, and consequently all other subsequent decisions.
1.The application for interim measures is dismissed.
2.Costs are reserved.