Case C-360/19: Judgment of the Court (Fifth Chamber) of 8 October 2020 (request for a preliminary ruling from the College van Beroep voor het bedrijfsleven — Netherlands) — Crown Van Gelder BV v Autoriteit Consument en Markt (Reference for a preliminary ruling — Internal market for electricity — Directive 2009/72/EC — Article 37 — Duties and powers of the regulatory authority — Out-of-court dispute settlement — Concept of ‘party having a complaint’ — Complaint submitted by a final customer against the operator of a transmission system to which that customer’s installation is not directly connected — Failure on the grid — No contractual relationship between that customer and the operator of that grid — Admissibility of the complaint)

ECLI:EU:UNKNOWN:62019CA0360

62019CA0360

October 8, 2020
With Google you find a lot.
With us you find everything. Try it now!

I imagine what I want to write in my case, I write it in the search engine and I get exactly what I wanted. Thank you!

Valentina R., lawyer

30.11.2020

Official Journal of the European Union

C 414/8

(Case C-360/19) (*)

(Reference for a preliminary ruling - Internal market for electricity - Directive 2009/72/EC - Article 37 - Duties and powers of the regulatory authority - Out-of-court dispute settlement - Concept of ‘party having a complaint’ - Complaint submitted by a final customer against the operator of a transmission system to which that customer’s installation is not directly connected - Failure on the grid - No contractual relationship between that customer and the operator of that grid - Admissibility of the complaint)

(2020/C 414/08)

Language of the case: Dutch

Referring court

Parties to the main proceedings

Applicant: Crown Van Gelder BV

Defendant: Autoriteit Consument en Markt

Other party: TenneT TSO BV

Operative part of the judgment

Article 37(11) of Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC must be interpreted as meaning that the regulatory authority may not dismiss a complaint submitted by a final customer against the operator of a transmission system, following a power failure in that system, on the ground that that final customer’s installation is connected not to that transmission system directly, but only to a distribution system fed by it.

(*) Language of the case: Dutch.

EurLex Case Law

AI-Powered Case Law Search

Query in any language with multilingual search
Access EUR-Lex and EU Commission case law
See relevant paragraphs highlighted instantly

Get Instant Answers to Your Legal Questions

Cancel your subscription anytime, no questions asked.Start 14-Day Free Trial

At Modern Legal, we’re building the world’s best search engine for legal professionals. Access EU and global case law with AI-powered precision, saving you time and delivering relevant insights instantly.

Contact Us

Tivolska cesta 48, 1000 Ljubljana, Slovenia